2013 BOND WATER/SEWER REPLACEMENT

VARIOUS LOCATIONS, Paris, TX 75460, Paris, TX, 75460

2013 BOND WATER/SEWER REPLACEMENT is a new construction project at VARIOUS LOCATIONS, Paris, in Lamar County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Feb 2020). The project has an estimated value of $23.0M.

Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB6811523
$23.0M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
4y 1mo
Duration
Registered:Mar 7, 2016
Start:Feb 1, 2016
Target:Feb 1, 2020
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

2013 BOND WATER/SEWER REPLACEMENT is a New Construction project located at VARIOUS LOCATIONS, Paris, TX 75460 in Paris, Texas. The project has an estimated value of $23.0M. CITY OF PARIS TX is the property owner and AECOM is the design firm of record. The project was registered with TDLR on March 7, 2016.

โ“Frequently Asked Questions

What is 2013 BOND WATER/SEWER REPLACEMENT?

2013 BOND WATER/SEWER REPLACEMENT is a new construction project at VARIOUS LOCATIONS in Paris, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Construction of 1.2 miles of sidewalk including curb ramps and crosswalks along Pine Bluff from N Main to 20th N

Is 2013 BOND WATER/SEWER REPLACEMENT open in Paris?

Construction on 2013 BOND WATER/SEWER REPLACEMENT is complete โ€” TDLR records show the project passed its required accessibility inspection in Feb 2020. The building is finished and very likely open.

Where is 2013 BOND WATER/SEWER REPLACEMENT located?

2013 BOND WATER/SEWER REPLACEMENT is located at VARIOUS LOCATIONS, Paris, TX, 75460, in Lamar County.

Who is the owner or developer of 2013 BOND WATER/SEWER REPLACEMENT?

CITY OF PARIS TX is the property owner/developer of record for 2013 BOND WATER/SEWER REPLACEMENT, per its TDLR project registration.

Who is the architect or design firm for 2013 BOND WATER/SEWER REPLACEMENT?

AECOM is the design firm of record for 2013 BOND WATER/SEWER REPLACEMENT, according to its TDLR filing.

How much does 2013 BOND WATER/SEWER REPLACEMENT cost and how big is it?

2013 BOND WATER/SEWER REPLACEMENT has an estimated construction value of $23.0M, based on its TDLR filing.

๐Ÿ“‹Scope of Work

Construction of 1.2 miles of sidewalk including curb ramps and crosswalks along Pine Bluff from N Main to 20th N

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 7, 2016
Inspection Complete
February 1, 2020
Construction Start
February 1, 2016
Expected Completion
February 1, 2020

๐Ÿ“…Project Timeline

Filed

Mar 7, 2016

Review Complete

Inspection Complete

Feb 1, 2020

Closed

Get alerts for Lamar

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists