๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

MCCULLOUGH AVENUE AREA DRAINAGE

MCCULLOUGH AVENUE, San Antonio, TX 78212, San Antonio, TX, 78212
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB6812769
$9.9M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
2y 1mo
Duration
Registered:Mar 23, 2016
Start:Jun 1, 2016
Target:Jun 12, 2018
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Proposed installation of an interceptor storm sewer system that will begin at Brooklyn & Euclid, extend to Wilmi

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 23, 2016
Construction Start
June 1, 2016
Expected Completion
June 12, 2018