๐ŸProject Closed๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

MIDWAY HIGH SCHOOL - CTE BLDG. ADDITION

8200 MARS DR., Waco, TX 76712, Waco, TX, 76712
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB6813207
$400K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
6 months
Duration
Registered:Mar 30, 2016
Start:Jun 1, 2016
Target:Dec 1, 2016
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Addition to C.T.E. building of approximately 4,000 square feet.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 30, 2016
Construction Start
June 1, 2016
Expected Completion
December 1, 2016