TRANSIT DEPT. ADDITIONS AND OFFICE EXP

800 S.E. 23RD AVE, Amarillo, TX 79103, Amarillo, TX, 79103
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB6814444
$835K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
11 months
Duration
Registered:Apr 15, 2016
Start:Jul 1, 2016
Target:May 31, 2017
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

New bus parking bay, new front and rear entrances, expansion of office space into existing bus parking bay

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 15, 2016
Construction Start
July 1, 2016
Expected Completion
May 31, 2017