Inspection Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
BARBARA DR DRAINAGE PROJ (23-01398)
BARBARA DRIVE, San Antonio, TX 78216, San Antonio, TX, 78216
Final Inspection85%
๐Project Metrics
TDLR #EABPRJB6821563$150K
Project Value
โ
Square Feet
โ
Cost/SqFt
7 months
Duration
Registered:Jul 28, 2016
Start:Jan 1, 2017
Target:Aug 1, 2017
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
Construct eastern channel storm drain improvements, roadway realignment and enhancement features consisting of s
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 28, 2016
Construction Start
January 1, 2017
Expected Completion
August 1, 2017
๐Related Projects
๐คSame Owner
$1.4M totalProperty Owner
๐ค
City of San Antonio
4 projects ยท $1.4M
View company profile
KATHERYN OTTO, P.E. 114 W. COMMERCE ST, SAN ANTONIO, TX 78207
Design Firm
๐๏ธ
CIVIL ENINEERING CONSULTANTS
4 projects ยท $28.1M
View company profile
MELISSA G. BYLER, P.E. 11550 IH 10 WEST, SUITE 395, SAN ANTONIO, TX 78230