๐Project Closed๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
POST OFFICE CENTER
5999 DEZAVALA RD, San Antonio, TX 78249, San Antonio, TX, 78249
Completed100%
๐Project Metrics
TDLR #EABPRJB7821133$391K
Project Value
โ
Square Feet
โ
Cost/SqFt
2 months
Duration
Registered:Jul 14, 2017
Start:Jul 1, 2017
Target:Sep 1, 2017
๐
Project Closed
Project has been completed and closed
๐Scope of Work
2"" parking cap, new islands, swales, striping
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 14, 2017
Project Closed
September 1, 2017
Construction Start
July 1, 2017
Expected Completion
September 1, 2017
๐Related Projects
๐๏ธSame Design Firm
$4.8M totalProperty Owner
๐ค
JESHULP C/O KYSE & ASSOC MGT CO
View all projects
RUSSEL KYSE 11120 WURZBACH #205, SAN ANTONIO, TX 78230
Design Firm
๐๏ธ
INDEPENDENT DESIGN
4 projects ยท $4.8M
View all projects
ALFONSO C. GUARNERO 1528 W. CONTOUR STE 202, SAN ANTONIO, TX 78212