📝Review Complete🔧 Renovation/Alteration💵 This project is privately funded, on private land for private use.
AFLAC
6222 RICHMOND Suite 255, Houston, TX 77042, Houston, TX, 77042
Construction50%
📊Project Metrics
TDLR #EABPRJB8803685$63K
Project Value
—
Square Feet
—
Cost/SqFt
2 months
Duration
Registered:Oct 26, 2017
Start:Nov 1, 2017
Target:Jan 1, 2018
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
Lease space remodel
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
October 26, 2017
Review Complete
October 26, 2017
Construction Start
November 1, 2017
Expected Completion
January 1, 2018
Property Owner
👤
FULLER THEOLOGICAL SEMINARY
View all projects
MICHAEL MURRY 10200 RICHMOND, HOUSTON, TX 77042