๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
CDBG SIDEWALK PROJECT DISTR II
DISTRICT I1, Laredo, TX 78040, Laredo, TX, 78040
Completed100%
๐Project Metrics
TDLR #EABPRJB8811784$180K
Project Value
โ
Square Feet
โ
Cost/SqFt
5 months
Duration
Registered:Mar 5, 2018
Start:Oct 1, 2017
Target:Mar 1, 2018
๐
Project Closed
Project has been completed and closed
๐Scope of Work
New sidewalk construction at the city right away
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
March 5, 2018
Project Closed
March 1, 2018
Construction Start
October 1, 2017
Expected Completion
March 1, 2018
๐Related Projects
๐คSame Owner
$12.1M total๐๏ธSame Design Firm
$700K totalProperty Owner
๐ค
CITY OF LAREDO
4 projects ยท $12.1M
View all projects
ROGELIO RIEVERA 1110 HOUSTON ST, LAREDO, TX 78040
Design Firm
๐๏ธ
City of Laredo Engineering Department
4 projects ยท $700K
View company profile
ROGELIO RIVERA 1110 HOUSTON ST, LAREDO, TX 78040