๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

MCKINNEY FBO TERMINAL

1508 INDUSTRIAL BLVD., Mckinney, TX 75069, Mckinney, TX, 75069
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB8818483
$6.9M
Project Value
17,326
Square Feet
$398/sqft
Cost/SqFt
3y 7mo
Duration
Registered:Jun 1, 2018
Start:Aug 1, 2018
Target:Jan 31, 2022
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

New Building Construction for a Fixed Base Operator (FBO) Airport Terminal.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 1, 2018
Construction Start
August 1, 2018
Expected Completion
January 31, 2022