๐Ÿ“Review Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

VIA BUS STOP & SIDEWALK IMPROVEMENTS CON

919 TOEPPERWEIN RD., Converse, TX 78109, Converse, TX, 78109
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB8821304
$307K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
7 months
Duration
Registered:Jul 11, 2018
Start:Aug 1, 2018
Target:Mar 1, 2019
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Construction of new bus stops

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 11, 2018
Construction Start
August 1, 2018
Expected Completion
March 1, 2019