🏁Project Closed🔧 Renovation/Alteration💵 This project involves public funds, public land, or is a Federally funded roadway project.

BCHM FLOOR REPLACEMENT & NEW RESTROOMS

100 EAST CEDAR, Angleton, TX 77515, Angleton, TX, 77515
Completed100%

📊Project Metrics

TDLR #EABPRJB8823803
$253K
Project Value
Square Feet
Cost/SqFt
6 months
Duration
Registered:Aug 14, 2018
Start:Sep 1, 2018
Target:Mar 1, 2019
🏁

Project Closed

Project has been completed and closed

📋Scope of Work

Replacement of existing first floor structure with new concrete and new first floor restrooms.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
August 14, 2018
Project Closed
March 1, 2019
Construction Start
September 1, 2018
Expected Completion
March 1, 2019