๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

COMPOSITE/DFW EXISTING BLDG MODIFICATION

1727 SOUTH MAIN STREET, Dfw Airport, TX 75261, Dfw Airport, TX, 75261
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB9805292
$100K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
2 months
Duration
Registered:Nov 15, 2018
Start:Jan 1, 2019
Target:Mar 1, 2019
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

52 space automobile parking lot expansion and exterior metal canopy renovation.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 15, 2018
Review Complete
November 15, 2018
Construction Start
January 1, 2019
Expected Completion
March 1, 2019

๐Ÿ“Location & Views

Open in MapsGet Directions|32.91600, -97.07959

Get alerts for Tarrant

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists