🏁Project Closed🔧 Renovation/Alteration💵 This project involves public funds, public land, or is a Federally funded roadway project.
2018 ADA & SRTS SIDEWALK IMPROVEMENT PROJECT
101 W. ABRAM ST, Arlington, TX 76010, Arlington, TX, 76010
Completed100%
📊Project Metrics
TDLR #TABS2019002804$545K
Project Value
8,900
Square Feet
$61/sqft
Cost/SqFt
6 months
Duration
Registered:Jan 16, 2019
Start:Mar 1, 2019
Target:Aug 31, 2019
🏁
Project Closed
Project has been completed and closed
📋Scope of Work
REMOVING AND REPLACING SIDEWALK THAT HAS BEEN IDENTIFIED AS BEING OUT OF COMPLIANCE AND ADDING SIDEWALK AT LOCATIONS TO MAKE A CONTINUOUS PEDESTRIAN PATH
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
January 16, 2019
Construction Start
March 1, 2019
Expected Completion
August 31, 2019
Property Owner
👤
CITY OF ARLINGTON RIGHT OF WAY
View all projects
101 W ABRAM STREET, ARLINGTON, Texas 76010
Design Firm
🏛️
CITY OF ARLINGTON PUBLIC WORKS AND TRANSPORTATION
View company profile
101 W. ABRAM, ARLINGTON, Texas 76010