๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

Terminal E GSE & Catering Renovation

3003 South Service Road, Dfw Airport, TX 75061, Dfw Airport, TX, 75061
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2019003191
$504K
Project Value
7,180
Square Feet
$70/sqft
Cost/SqFt
11 months
Duration
Registered:Jan 23, 2019
Start:Feb 15, 2019
Target:Jan 15, 2020
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Ramp level renovations to existing Terminal for GSE & Catering spaces to serve Terminal E Satellite, Floor, ceiling and wall finishes to be updated throughout. Addition of fenced areas for supply storage

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
January 23, 2019
Construction Start
February 15, 2019
Expected Completion
January 15, 2020