🏁Project Closed🔧 Renovation/Alteration💵 This project involves public funds, public land, or is a Federally funded roadway project.
US 90
US 90, Columbus, TX 78934, Columbus, TX, 78934
Completed100%
📊Project Metrics
TDLR #TABS2019004331$94K
Project Value
6,921
Square Feet
$14/sqft
Cost/SqFt
1y 7mo
Duration
Registered:Feb 7, 2019
Start:Dec 1, 2019
Target:Jun 21, 2021
🏁
Project Closed
Project has been completed and closed
📋Scope of Work
Construct One-Way bridge and approaches.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
February 7, 2019
Construction Start
December 1, 2019
Expected Completion
June 21, 2021