🏁Project Closed🔧 Renovation/Alteration💵 This project involves public funds, public land, or is a Federally funded roadway project.

MAUER ROAD NTMP

MAUER AND GALLAGHER, El Paso, TX 79915, El Paso, TX, 79915
Completed100%

📊Project Metrics

TDLR #TABS2019007590
$80K
Project Value
10,000
Square Feet
$8/sqft
Cost/SqFt
6 months
Duration
Registered:Mar 21, 2019
Start:Jun 1, 2019
Target:Dec 1, 2019
🏁

Project Closed

Project has been completed and closed

📋Scope of Work

INSTALLATION OF TRAFFIC CALMING DEVICES AT CITY INTERSECTION

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
March 21, 2019
Construction Start
June 1, 2019
Expected Completion
December 1, 2019