📝Review Complete🏗️ New Construction💵 This project involves public funds, public land, or is a Federally funded roadway project.
Farmersville Wastewater treament plant #3
County road 550, Farmersville, TX 75442, Farmersville, TX, 75442
Construction50%
📊Project Metrics
TDLR #TABS2019009490$600K
Project Value
2,685
Square Feet
$223/sqft
Cost/SqFt
3y 9mo
Duration
Registered:Apr 16, 2019
Start:Jan 31, 2020
Target:Sep 30, 2023
📝
Review Complete
Design review complete, construction may proceed
📋Scope of Work
construction of new adminstration building for a new wastewater treatment plant
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
April 16, 2019
Construction Start
January 31, 2020
Expected Completion
September 30, 2023
Property Owner
👤
CITY OF FARMERSVILLE ATTN BEN WHITE
View company profile
205 S. Main Street, Farmersville, Texas 75442
Design Firm
🏛️
Quorum Architect, Inc.
View all projects
707 W. Vickery Blvd Suite 101, fort worth, Texas 76104