๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

Bridgeland Parkland Village Section 28/Pipeline

Roaming Bison Trail & Balmorhea Park Drive, Cypress, TX 77433, Cypress, TX, 77433
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2019011134
$650K
Project Value
195,500
Square Feet
$3/sqft
Cost/SqFt
4 months
Duration
Registered:May 8, 2019
Start:Jun 3, 2019
Target:Sep 30, 2019
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Concrete Trails, Planting, Irrigation, Monument Sign w/ Graphics and Lighting, Grading and Drainage

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 8, 2019
Construction Start
June 3, 2019
Expected Completion
September 30, 2019