Sun Vision Warehouse-Church on the 2nd Floor
๐Project Metrics
TDLR #TABS2019014397Review Complete
Design review complete, construction may proceed
๐Scope of Work
Construction of 2nd floor into a church. Spaces include Sanctuary, Fellow-ship, gathering area, classrooms, men and women's restrooms.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
๐Related Projects
๐๏ธSame Design Firm
$2.8M total๐Related City Permits
Building permits found at or near this location
Replacement of complete existing central heat and air system with or without duct work
Relocated existing overhead electrical service drop and meter. New permanent meter loop pole will be installed remaining overhead. AE Design and Criteria Standards shall be followed.
Installation of 1 EV Charger & Shutdown needed for Gateway install
Installation of 27.84kW system & 1 Powerwall
Replacement of complete existing central heat and air system with or without duct work LIKE FOR LIKE: 4 ton gas upflow system