โœ…Inspection Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Thistle Down Street Reconstruction

Clearlake to Tammaron, San Antonio, TX 78217, San Antonio, TX, 78217
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2019014762
$278K
Project Value
3,400
Square Feet
$82/sqft
Cost/SqFt
4 months
Duration
Registered:Jun 25, 2019
Start:Sep 1, 2019
Target:Dec 31, 2019
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Install new curb ramps

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 25, 2019
Inspection Complete
December 31, 2019
Construction Start
September 1, 2019
Expected Completion
December 31, 2019

Get alerts for Bexar

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists