๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

ACE Cash Express - 9th floor

300 East John Carpenter Freeway, Suite 900, Irving, TX 75062, Irving, TX, 75062
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2019017138
$750K
Project Value
22,000
Square Feet
$34/sqft
Cost/SqFt
3 months
Duration
Registered:Jul 29, 2019
Start:Sep 1, 2019
Target:Dec 2, 2019
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

interior alteration for general office use

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 29, 2019
Construction Start
September 1, 2019
Expected Completion
December 2, 2019

๐Ÿ“Location & Views

Open in MapsGet Directions|32.86326, -96.93964