๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Ervin-Hobbs Connector
1202 Ervin Street, League City, TX 77573, League City, TX, 77573
Completed100%
๐Project Metrics
TDLR #TABS2019017777$5.1M
Project Value
40,000
Square Feet
$128/sqft
Cost/SqFt
1y 1mo
Duration
Registered:Aug 6, 2019
Start:Aug 1, 2019
Target:Sep 1, 2020
๐
Project Closed
Project has been completed and closed
๐Scope of Work
New 10-wide trail along both sides, 3,200 LF curb and roadway an storm sewer.2,700 LF detention channel a 12" and 24" water line
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 6, 2019
Construction Start
August 1, 2019
Expected Completion
September 1, 2020
๐Related Projects
๐คSame Owner
$51.9M total๐๏ธSame Design Firm
$5.9M totalProperty Owner
๐ค
City of League City
4 projects ยท $51.9M
View all projects
300 W Walker Street, League City, Texas 77573
Design Firm
๐๏ธ
R G Miller Engineers Inc.
2 projects ยท $5.9M
View all projects
16340 Park Ten Place, Suite 350, Houston, Texas 77084