๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

River Park Phase 1A Improvements

900 River Park Road, Pleasanton, TX 78064, Pleasanton, TX, 78064
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020000298
$705K
Project Value
3,300
Square Feet
$213/sqft
Cost/SqFt
4 months
Duration
Registered:Sep 5, 2019
Start:Jun 11, 2019
Target:Oct 7, 2019
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

The Work of Project is defined by the Contract Documents and consists of a restroom building, two covered pavilions, concrete sidewalks, lighting, site grading, paving, storm water conveyance, and utilities.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 5, 2019
Construction Start
June 11, 2019
Expected Completion
October 7, 2019