📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.

Santos Warehouse Facility II

313 Crossroads Street, Laredo, TX 78045, Laredo, TX, 78045
Construction50%

📊Project Metrics

TDLR #TABS2020001196
$1.5M
Project Value
39,803
Square Feet
$38/sqft
Cost/SqFt
7 months
Duration
Registered:Sep 18, 2019
Start:Oct 1, 2019
Target:May 1, 2020
📝

Review Complete

Design review complete, construction may proceed

📋Scope of Work

Office/Warehouse Facility

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
September 18, 2019
Review Complete
September 18, 2019
Construction Start
October 1, 2019
Expected Completion
May 1, 2020