๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

Interior Alterations to 8630 Burnham ste.100

8360 Burnham Ste.100, El Paso, TX 79907, El Paso, TX, 79907
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020003791
$230K
Project Value
20,000
Square Feet
$12/sqft
Cost/SqFt
4 months
Duration
Registered:Oct 23, 2019
Start:Oct 20, 2019
Target:Feb 28, 2020
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

new walls, new ceiling, new lighting, new offices, existing restroom to remain

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 23, 2019
Construction Start
October 20, 2019
Expected Completion
February 28, 2020

๐Ÿ”—Related Projects

๐Ÿ›๏ธSame Design Firm

$410K total