๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

HPISD - Highlander Stadium

4233 Grassmere Lane, Dallas, TX 75205, Dallas, TX, 75205
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020004165
$5.7M
Project Value
38,598
Square Feet
$146/sqft
Cost/SqFt
4 months
Duration
Registered:Oct 29, 2019
Start:Apr 1, 2020
Target:Aug 1, 2020
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Highlander Stadium Renovation - only grandstands building at north side and field house building

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 29, 2019
Construction Start
April 1, 2020
Expected Completion
August 1, 2020