๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

New worship center, children's area, & office

2400 State Hwy 35 S, Port Lavaca, TX 77979, Port Lavaca, TX, 77979
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020005574
$2.2M
Project Value
15,000
Square Feet
$147/sqft
Cost/SqFt
10 months
Duration
Registered:Nov 18, 2019
Start:Jan 1, 2020
Target:Nov 1, 2020
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Pre-engineered metal building with concrete foundation, electrical, plumbing, HVAC, & parking lot.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 18, 2019
Construction Start
January 1, 2020
Expected Completion
November 1, 2020