๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Jerry McDonald Ball Field

113 South Alister St., Port Aransas, TX 78373, Port Aransas, TX, 78373
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020005894
$950K
Project Value
400
Square Feet
$2.38K/sqft
Cost/SqFt
7 months
Duration
Registered:Nov 21, 2019
Start:Dec 15, 2019
Target:Jun 30, 2020
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Concession Building, Softball Field, Dugouts

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 21, 2019
Project Closed
June 30, 2020
Construction Start
December 15, 2019
Expected Completion
June 30, 2020

๐Ÿ“Location & Views

Open in MapsGet Directions|27.83221, -97.06332

Get alerts for Nueces

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists