๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

1930 Hanby Stadium Locker Addition/Renovation

508 E Davis STreet, Mesquite, TX 75049, Mesquite, TX, 75049
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020009024
$1.8M
Project Value
2,700
Square Feet
$667/sqft
Cost/SqFt
5 months
Duration
Registered:Jan 13, 2020
Start:Feb 19, 2020
Target:Aug 1, 2020
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Locker Room Addition and Renovation at Existing Stadium

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
January 13, 2020
Project Closed
August 1, 2020
Construction Start
February 19, 2020
Expected Completion
August 1, 2020