Friona ISD Band Hall Addition and Security Reno -Vol.-III
Friona ISD Band Hall Addition and Security Reno -Vol.-III is a additions to existing building project at 7th & Etta Street, Friona, in Parmer County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Jan 2022). The project has an estimated value of $3.1M across about 23,000 sq ft.
๐Project Metrics
TDLR #TABS2020009303Project Closed
Project has been completed and closed
Friona ISD Band Hall Addition and Security Reno -Vol.-III is a Additions to Existing Building project located at 7th & Etta Street, Friona, TX 79035 in Friona, Texas. The project has an estimated value of $3.1M covering 23,000 sq ft. Friona Independent School District is the property owner and Parkhill, Smith & Cooper, Inc. is the design firm of record. The project was registered with TDLR on January 16, 2020.
โFrequently Asked Questions
What is Friona ISD Band Hall Addition and Security Reno -Vol.-III?
Friona ISD Band Hall Addition and Security Reno -Vol.-III is a additions to existing building project at 7th & Etta Street in Friona, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Work includees the addition of a new band hall that will also be a storm shelter. Remove and replace existing exterior aluminum windows and exterior hollow metal doors. Renovate the admin area and provide secure vestibule and reno existiโฆ
Is Friona ISD Band Hall Addition and Security Reno -Vol.-III open in Friona?
Construction on Friona ISD Band Hall Addition and Security Reno -Vol.-III is complete โ TDLR records show the project passed its required accessibility inspection in Jan 2022. The building is finished and very likely open.
Where is Friona ISD Band Hall Addition and Security Reno -Vol.-III located?
Friona ISD Band Hall Addition and Security Reno -Vol.-III is located at 7th & Etta Street, Friona, TX, 79035, in Parmer County.
Who is the owner or developer of Friona ISD Band Hall Addition and Security Reno -Vol.-III?
Friona Independent School District is the property owner/developer of record for Friona ISD Band Hall Addition and Security Reno -Vol.-III, per its TDLR project registration.
Who is the architect or design firm for Friona ISD Band Hall Addition and Security Reno -Vol.-III?
Parkhill, Smith & Cooper, Inc. is the design firm of record for Friona ISD Band Hall Addition and Security Reno -Vol.-III, according to its TDLR filing.
How much does Friona ISD Band Hall Addition and Security Reno -Vol.-III cost and how big is it?
Friona ISD Band Hall Addition and Security Reno -Vol.-III has an estimated construction value of $3.1M and approximately 23,000 square feet (about $135/sqft), based on its TDLR filing.
๐Scope of Work
Work includees the addition of a new band hall that will also be a storm shelter. Remove and replace existing exterior aluminum windows and exterior hollow metal doors. Renovate the admin area and provide secure vestibule and reno existing restrooms.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
๐ Project Timeline
Filed
Jan 16, 2020
Review Complete
Inspection Complete
Closed
Jan 7, 2022