๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

Second Floor Office Renovation - Phase 2

1111 West Loop 289, Lubbock, TX 79416, Lubbock, TX, 79416
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020010662
$90K
Project Value
625
Square Feet
$144/sqft
Cost/SqFt
3 months
Duration
Registered:Feb 4, 2020
Start:Mar 1, 2020
Target:Jun 1, 2020
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Renovating a portion of a large storage space into three individual offices

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
February 4, 2020
Construction Start
March 1, 2020
Expected Completion
June 1, 2020