๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Additional Sidewalk at Mora Elementary School
1520 American Lotus, San Antonio, TX 78245, San Antonio, TX, 78245
Completed100%
๐Project Metrics
TDLR #TABS2020014189$50K
Project Value
6,866
Square Feet
$7/sqft
Cost/SqFt
1 months
Duration
Registered:Mar 23, 2020
Start:Apr 13, 2020
Target:May 13, 2020
๐
Project Closed
Project has been completed and closed
๐Scope of Work
[1:11 PM] Benjamin Powell Provide new 6' wide concrete sidewalk from the County right-of-way to the school. Project to include utilities and all other work as shown on the construction documents.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
March 23, 2020
Construction Start
April 13, 2020
Expected Completion
May 13, 2020
๐Related Projects
๐คSame Owner
$92.3M totalProperty Owner
๐ค
Northside Independent School District
Contact: Pollyanne Johnsone
4 projects ยท $92.3M
View all projects
5900 Evers Road Building E, San Antonio, Texas 78238
Design Firm
๐๏ธ
MOY TARIN RAMIREZ ENGINEERS
4 projects ยท $14.8M
View company profile
12770 Cimarron Path Suite 100, San Antonio, Texas 78249