๐Ÿ“Review Complete๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project is privately funded, on private land for private use.

Frisco Municipal Court Adaptive Reuse

8450 Moore St, Frisco, TX 75034, Frisco, TX, 75034
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020015117
$8.0M
Project Value
23,715
Square Feet
$337/sqft
Cost/SqFt
11 months
Duration
Registered:Apr 6, 2020
Start:Jul 1, 2020
Target:Jun 1, 2021
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Adaptive reuse of a 17,395 SF existing Senior Center to a new Municipal court facility. Scope also includes 6,300 SF of addition which makes the total project 23,715 SFT approximately.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 6, 2020
Construction Start
July 1, 2020
Expected Completion
June 1, 2021