๐Project Closed๐ง Additions to Existing Building๐ต This project is privately funded, on private land for private use.
Labatt Houston Phase IV
6650 Pine Vista, Houston, TX 77092, Houston, TX, 77092
Completed100%
๐Project Metrics
TDLR #TABS2020016202$4.0M
Project Value
38,967
Square Feet
$103/sqft
Cost/SqFt
8 months
Duration
Registered:Apr 24, 2020
Start:Dec 1, 2020
Target:Aug 1, 2021
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Freezer Addition to existing
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
April 24, 2020
Construction Start
December 1, 2020
Expected Completion
August 1, 2021
๐Related Projects
๐คSame Owner
$22.8M total๐๏ธSame Design Firm
$25.1M totalProperty Owner
๐ค
LABATT FOOD SEVICE
Contact: Craig Witten
4 projects ยท $22.8M
View company profile
6650 Pine Visata, Houston, Texas 77092
Design Firm
๐๏ธ
TEAM Group Ltd
4 projects ยท $25.1M
View all projects
1001 W Euless Blvd Ste 209, Euless, Texas 76040