Tolar High School Secondary Gym

301 Rock Church Highway, Tolar, TX 76476, Tolar, TX, 76476
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020016901
$1.4M
Project Value
10,800
Square Feet
$130/sqft
Cost/SqFt
6 months
Duration
Registered:May 6, 2020
Start:Mar 31, 2021
Target:Sep 30, 2021
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

New Secondary Gym with public restrooms and locker rooms

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 6, 2020
Construction Start
March 31, 2021
Expected Completion
September 30, 2021