📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.

Lance Industries Baytown

1603 Thompson Park Drive, Baytown, TX 77521, Baytown, TX, 77521
Construction50%

📊Project Metrics

TDLR #TABS2020017298
$3.4M
Project Value
40,000
Square Feet
$85/sqft
Cost/SqFt
6 months
Duration
Registered:May 13, 2020
Start:Jul 1, 2020
Target:Dec 31, 2020
📝

Review Complete

Design review complete, construction may proceed

📋Scope of Work

New Rental Equipment Sales and Service Center

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
May 13, 2020
Construction Start
July 1, 2020
Expected Completion
December 31, 2020