๐Project Closed๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
USAA F750 Switchgear Replacement
9800 Fredericksburg Road, San Antonio, TX 78288, San Antonio, TX, 78288
Completed100%
๐Project Metrics
TDLR #TABS2020019412$2.7M
Project Value
840
Square Feet
$3.21K/sqft
Cost/SqFt
1y 4mo
Duration
Registered:Jun 23, 2020
Start:Jul 1, 2020
Target:Nov 1, 2021
๐
Project Closed
Project has been completed and closed
๐Scope of Work
THE WORK CONSISTS OF THE REPLACEMENT OF THREE 15 kV SWITCHGEAR LINEUPS IN THE USAA HOME OFFICE BUILDING (HOB) LOCATED ON THE SERVICE LEVEL (P4) NEAR THE SOUTH END OF 'B' BUILDING. THE NEW SWITCHGEAR WILL BE INSTALLED IN A NEW ELECTRICAL ROOM TO BE C
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
June 23, 2020
Construction Start
July 1, 2020
Expected Completion
November 1, 2021
๐Related Projects
Property Owner
Design Firm
๐๏ธ
Alamo Architects
4 projects ยท $122.3M
View all projects
1512 South Flores, San Antonio, Texas 78204