🏁Project Closed🔧 Renovation/Alteration💵 This project is privately funded, on private land for private use.
Court's Parking Lot Paving Repairs
2830 South Main, Stafford, TX 77477, Stafford, TX, 77477
Completed100%
📊Project Metrics
TDLR #TABS2020021028$78K
Project Value
10,970
Square Feet
$7/sqft
Cost/SqFt
2 months
Duration
Registered:Jul 23, 2020
Start:Aug 3, 2020
Target:Oct 12, 2020
🏁
Project Closed
Project has been completed and closed
📋Scope of Work
Remove Existing Asphalt Parking Lot & replace with Concrete/10,077 sf; Replace Conc Sidewalk 893 sf; Relocate Dumpster & Enclose; Provide necessary ADA ramp, parking, striping & signage
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
July 23, 2020
Construction Start
August 3, 2020
Expected Completion
October 12, 2020
Property Owner
👤
CHRIS COURT COURT PROPERTIES
Contact: Chris Court
View company profile
2830 South Main, Stafford, Texas 77477