7th Street Paving & Drainage Improvements
7th Street -Main St to Fairmont Parkway, La Porte, TX 77571, La Porte, TX, 77571
Final Inspection85%
๐Project Metrics
TDLR #TABS2020022454$347K
Project Value
35,880
Square Feet
$10/sqft
Cost/SqFt
1y 9mo
Duration
Registered:Aug 19, 2020
Start:Oct 1, 2020
Target:Jul 1, 2022
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
Sidewalks along 7th Street in La Porte from Fairmont Pkwy to Main Street
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 19, 2020
Inspection Complete
July 1, 2022
Construction Start
October 1, 2020
Expected Completion
July 1, 2022
Property Owner
๐ค
CITY OF LA PORTE TEXAS
Contact: Don Pennell
4 projects ยท $46.3M
View company profile
2963 N 23rd Street, La Porte, Texas 77571
Design Firm
๐๏ธ
Cobb, Fendley & Associates ,Inc
View all projects
1920 Country Place Parkway #400, Pearland, Texas 77584