COSA Dist 6 Ped Improvements - Northglen Dr.
Northglen Dr from Shady Grove to Marbach Rd., San Antonio, TX 78264, San Antonio, TX, 78264
Completed100%
๐Project Metrics
TDLR #TABS2021004496$53K
Project Value
4,960
Square Feet
$11/sqft
Cost/SqFt
2 months
Duration
Registered:Nov 17, 2020
Start:Dec 7, 2020
Target:Feb 7, 2021
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Installation of sidewalk.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
November 17, 2020
Project Closed
February 7, 2021
Construction Start
December 7, 2020
Expected Completion
February 7, 2021
๐Related Projects
๐คSame Owner
$30.6M totalProperty Owner
๐ค
City of San Antonio
4 projects ยท $30.6M
View all projects
114 W. Commerce, 6th Floor, San Antonio, Texas 78205
Design Firm
๐๏ธ
Jacobs Engineering Group Inc.
4 projects ยท $2.6M
View all projects
911 Central parkway N, Ste. 200, San Antonio, Texas 78232