๐Ÿ“Review Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

Martin Bionics

850 W. John Carpenter Fwy, Irving, TX 75039, Irving, TX, 75039
Construction50%

๐Ÿ“ŠProject Metrics

TDLR #TABS2021011478
$280K
Project Value
4,911
Square Feet
$57/sqft
Cost/SqFt
5 months
Duration
Registered:Mar 18, 2021
Start:Apr 1, 2021
Target:Aug 31, 2021
๐Ÿ“

Review Complete

Design review complete, construction may proceed

๐Ÿ“‹Scope of Work

Interior renovation of existing facility

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 18, 2021
Construction Start
April 1, 2021
Expected Completion
August 31, 2021