📝Review Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.

DCF CHURCH

203 FENN RD, Rosharon, TX 77583, Rosharon, TX, 77583
Construction50%

📊Project Metrics

TDLR #TABS2021015215
$1.2M
Project Value
9,090
Square Feet
$132/sqft
Cost/SqFt
8 months
Duration
Registered:May 10, 2021
Start:Jul 12, 2021
Target:Mar 14, 2022
📝

Review Complete

Design review complete, construction may proceed

📋Scope of Work

NEW BUILD-OT CHURCH ON A 5 ACRE TRACT

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
May 10, 2021
Review Complete
May 10, 2021
Construction Start
July 12, 2021
Expected Completion
March 14, 2022