Delta Hotels by Marriott

306 Travis Street, Wichita Falls, TX 76301, Wichita Falls, TX, 76301
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2021018125
$31.7M
Project Value
137,329
Square Feet
$231/sqft
Cost/SqFt
1y 11mo
Duration
Registered:Jun 19, 2021
Start:Sep 20, 2021
Target:Aug 1, 2023
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

This is a 7-story, 200-room hotel to be owner by OH-Wichita Falls, LLC attached to a convention center facility to be owner by the City of Wichita Falls, TX.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 19, 2021
Construction Start
September 20, 2021
Expected Completion
August 1, 2023