๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

2018 Bond Year 3 Contract 12

Intersection of Clebune Road and Hulen, Fort Worth, TX 76123, Fort Worth, TX, 76123
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2021019848
$53K
Project Value
6,400
Square Feet
$8/sqft
Cost/SqFt
11 months
Duration
Registered:Jul 14, 2021
Start:Oct 1, 2020
Target:Aug 30, 2021
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Reconstruct Cleburne Road with curb/gutter and sidewalks.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 14, 2021
Construction Start
October 1, 2020
Expected Completion
August 30, 2021

Quick Actions

TDLR ID: TABS2021019848

Design Firm

Registered Accessibility Specialist

๐Ÿ“‹
JAMES LEE,KRUEGER
RAS #372