Inspection Complete🏗️ New Construction💵 This project is privately funded, on private land for private use.

National Medal of Honor Museum

1905 East Randol Mill Road, Arlington, TX 76011, Arlington, TX, 76011
Final Inspection85%

📊Project Metrics

TDLR #TABS2021023144
$99.2M
Project Value
101,300
Square Feet
$979/sqft
Cost/SqFt
2y 7mo
Duration
Registered:Aug 30, 2021
Start:Mar 1, 2022
Target:Sep 30, 2024

Inspection Complete

Final inspection completed, awaiting project closure

📋Scope of Work

Complete construction of the building and all site work and landscaping

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
August 30, 2021
Construction Start
March 1, 2022
Expected Completion
September 30, 2024