Lipan 2021 Bond Projects is a additions to existing building project at 211 N. Kickapoo St., Lipan, in Hood County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Aug 2022). The project has an estimated value of $7.0M across about 21,300 sq ft.
๐Project Metrics
TDLR #TABS2021023181Project Closed
Project has been completed and closed
Lipan 2021 Bond Projects is a Additions to Existing Building project located at 211 N. Kickapoo St., Lipan, TX 76462 in Lipan, Texas. The project has an estimated value of $7.0M covering 21,300 sq ft. Lipan ISD is the property owner and Corgan is the design firm of record. The project was registered with TDLR on August 30, 2021.
โFrequently Asked Questions
What is Lipan 2021 Bond Projects?
Lipan 2021 Bond Projects is a additions to existing building project at 211 N. Kickapoo St. in Lipan, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Lipan 2021 Bond Projects will include (3) separate additions to an existing K-12 campus. The design includes a pre-engineered metal shop building, a (6) classroom addition to the existing HS, and a (6) classroom addition to the existing ES.
Is Lipan 2021 Bond Projects open in Lipan?
Construction on Lipan 2021 Bond Projects is complete โ TDLR records show the project passed its required accessibility inspection in Aug 2022. The building is finished and very likely open.
Where is Lipan 2021 Bond Projects located?
Lipan 2021 Bond Projects is located at 211 N. Kickapoo St., Lipan, TX, 76462, in Hood County.
Who is the owner or developer of Lipan 2021 Bond Projects?
Lipan ISD is the property owner/developer of record for Lipan 2021 Bond Projects, per its TDLR project registration.
Who is the architect or design firm for Lipan 2021 Bond Projects?
Corgan is the design firm of record for Lipan 2021 Bond Projects, according to its TDLR filing.
How much does Lipan 2021 Bond Projects cost and how big is it?
Lipan 2021 Bond Projects has an estimated construction value of $7.0M and approximately 21,300 square feet (about $329/sqft), based on its TDLR filing.
๐Scope of Work
Lipan 2021 Bond Projects will include (3) separate additions to an existing K-12 campus. The design includes a pre-engineered metal shop building, a (6) classroom addition to the existing HS, and a (6) classroom addition to the existing ES.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
๐ Project Timeline
Filed
Aug 30, 2021
Review Complete
Inspection Complete
Closed
Aug 15, 2022