KUNG FU TEA BUILD-OUT

1275 ELDRIDGE PARKWAY SUITE 195, Houston, TX 77070, Houston, TX, 77070
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2021023230
$120K
Project Value
1,275
Square Feet
$94/sqft
Cost/SqFt
11 months
Duration
Registered:Aug 30, 2021
Start:Oct 1, 2021
Target:Aug 20, 2022
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

INTERIOR BUILD-OUT OF A TEA HOUSE

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
August 30, 2021
Construction Start
October 1, 2021
Expected Completion
August 20, 2022