Inspection Complete🔧 Renovation/Alteration💵 This project involves public funds, public land, or is a Federally funded roadway project.

Palm Plaza Modernization

810 Mayberry Rd., Mission, TX 78572, Mission, TX, 78572
Final Inspection85%

📊Project Metrics

TDLR #TABS2022000034
$1.3M
Project Value
6,000
Square Feet
$217/sqft
Cost/SqFt
2y 4mo
Duration
Registered:Sep 1, 2021
Start:Oct 18, 2021
Target:Jan 31, 2024

Inspection Complete

Final inspection completed, awaiting project closure

📋Scope of Work

Elevator Replacement, Restroom Renovation, Parking Renovation, Systems upgrades, Asbestos Abatement, misc. renovations.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
September 1, 2021
Construction Start
October 18, 2021
Expected Completion
January 31, 2024