๐Review Complete๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Bottleneck Intersection Improvements - Package 1
Broadway Blvd at IH-30 & Plano Rd at Buckingham Rd, Garland, TX 75043, Garland, TX, 75043
Construction50%
๐Project Metrics
TDLR #TABS2022000483$273K
Project Value
175
Square Feet
$1.56K/sqft
Cost/SqFt
3y 5mo
Duration
Registered:Sep 8, 2021
Start:Jan 3, 2022
Target:May 15, 2025
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
New Streets, Driveways, Sidewalks and Curb Ramps
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
September 8, 2021
Review Complete
September 8, 2021
Construction Start
January 3, 2022
Expected Completion
May 15, 2025
๐Related Projects
๐คSame Owner
$340K totalProperty Owner
๐ค
City of Garland - Bond Program 2019
Contact: Doug Mikeworth
2 projects ยท $340K
View company profile
200 North Fifth Street, Garland, Texas 75040
Design Firm
๐๏ธ
Teague Nall and Perkins, Incorporated
4 projects ยท $10.4M
View all projects
825 Watters Creek Boulevard - Suite #M300, Allen, Texas 75013