๐Project Closed๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
UTSA MS Update Space for Adaptive Testing
One UTSA Circle, San Antonio, TX 78249, San Antonio, TX, 78249
Completed100%
๐Project Metrics
TDLR #TABS2022001888$280K
Project Value
900
Square Feet
$311/sqft
Cost/SqFt
4 months
Duration
Registered:Sep 28, 2021
Start:Nov 1, 2021
Target:Feb 25, 2022
๐
Project Closed
Project has been completed and closed
๐Scope of Work
900 square foot renovation to existing offices/ testing space with infrastructure to support.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
September 28, 2021
Construction Start
November 1, 2021
Expected Completion
February 25, 2022